Free CISA Certification Practice Questions:
You have recently been hired by a firm to assess an organization's recoverability in case of a disaster. You are in the process of reviewing the organization's disaster recovery plan. While reviewing the plan, you learned that the organization had contracted with an outside consulting firm to develop the recovery plan. Which of the following is the MOST appropriate action to take?
A) Review the plan to ensure that all mission-critical applications have been identified
B) Review the plan to ensure adequate input from the relevant business and IS personnel during plan development
C) Review the plan to ensure that the key decisions dictated by the consulting firm are appropriate for the organization
D) Review the plan to determine whether all aspects of the current processes are described in detail
E) Review the plan to determine whether the methodology used by the consulting firm was appropriate for the organization
-
[Ans: B]
As each organization is unique, a recovery
plan should be tailored to an organization's
specific needs and requirements. Adequate
input from the relevant business and IS
personnel during plan development is critical
in order to identify and prioritize the
business processes that are uniquely critical
to the livelihood of the organization.
A comprehensive evaluation of the environment
must involve the input from senior management,
end-users, key IS staff and should identify
the following:
1) The most critical business processes across
the entire enterprise
2) The maximum outage that a business process
can sustain before it severely impacts the well-being
of the company
3) The financial, productivity and personal impacts
of an extended business disruption
4) An assessment of short-term business impacts
and permanent business losses
5) The priority of business process recovery
Although ensuring that all mission critical
applications are identified is an important
aspect of the recovery plan, such a goal
cannot be achieved without first ensuring
that the key business and IS personnel are
identified and involved during the recovery
plan development.
Reviewing the plan to determine whether
all processes are described in detail is
NOT appropriate. During a disaster, only
mission-critical applications / systems
will likely be recovered. Non-critical systems
will be ignored. Hence, a recovery plan
should not document all the processes in
detail, but rather describe the procedures
necessary to recover the mission-critical
applications. Since many of the current
processes may not be relevant during a disaster,
documenting the un-necessary process may
actually hinder and interfere with the recovery
process.
While reviewing the methodology used by
the consulting firm may be relevant to the
audit, it is NOT as important as ensuring
that key IS personnel were involved during
the plan development. Lastly, a consulting
firm should NOT dictate key decisions during
recovery planning. Instead, those who are
intimately involved in the management and
operations of the business, such as senior
management and key IS staff, should be involved
in the key decision making process. In fact,
if a consulting firm was making key decisions
on behalf of the organization, this would
constitute a material weakness.
References: http://www.ffiec.gov/ffiecinfobase/booklets/bcp/bcp_toc.htm